Skip to content

CA Intermediate · Auditing and Ethics · Audit Documentation

CA Tanvi completed the audit of Brahmaputra Foods Ltd, and the auditor's report is dated 10 August 2026. Under SA 230 and the quality management standards, by when must the final audit file assembly ordinarily be completed?

The final audit file should be assembled within 60 days after the date of the auditor's report, which here means by 9 October 2026. Thirty days is not the prescribed period, and retention periods are a separate matter from the time allowed to complete file assembly.

  1. AWithin 60 days following the date of the auditor's report, i.e. by 9 October 2026Correct
  2. BWithin 30 days following the date of the auditor's report, i.e. by 9 September 2026
  3. CWithin 7 years from the end of the financial year
  4. DBefore the date of the auditor's report

Explanation

SA 230 requires the auditor to complete the assembly of the final audit file on a timely basis after the date of the auditor's report, and the ICAI standards specify an assembly period not exceeding 60 days. 10 August plus 60 days is 9 October. The 30-day option is a shorter period not prescribed, and the 7-year option confuses retention with assembly.

Did you get it right without looking?

One question tells you little. A timed set on Audit Documentation shows your real accuracy, how long you take and where you lose marks.

More Audit Documentation questions