CA Final · Integrated Business Solutions (Multidisciplinary Case Study with Strategic Management) · Strategic Cost & Performance Management

Case: Kaveri Components Ltd, Pune, budgeted production of 10,000 units for the month at a standard variable cost of Rs 120 per unit and budgeted fixed overheads of Rs 3,00,000. Actual production was 11,000 units, and actual fixed overheads were Rs 3,20,000. Under a flexible budget, what is the flexed budget allowance for total fixed overheads at 11,000 units, and the fixed overhead expenditure variance?

The flexed fixed overhead allowance remains Rs 3,00,000 because fixed costs do not vary with output in the relevant range. Actual spending was Rs 3,20,000, so the expenditure variance is Rs 20,000 adverse.

  1. ARs 3,30,000; Rs 10,000 favourable
  2. BRs 3,00,000; Rs 20,000 adverseCorrect
  3. CRs 3,00,000; Rs 20,000 favourable
  4. DRs 3,30,000; Rs 20,000 adverse

Explanation

Fixed overheads do not change with activity within the relevant range, so the flexed allowance stays at Rs 3,00,000. Expenditure variance = budgeted 3,00,000 - actual 3,20,000 = Rs 20,000 adverse. Scaling fixed cost to Rs 3,30,000 wrongly treats it as variable.