CMA Foundation · Fundamentals of Business Laws and Business Communication · Discharge of Contracts

Dev owes Esha a fixed sum payable on a specified day and fails to pay on that day. Esha, because of the delay, cannot pay her own debts and is ruined. What can Esha recover from Dev under the Act's illustration?

Esha can recover the principal sum with interest up to the day of payment. She cannot recover the loss from being ruined, because that is remote and indirect loss, which Section 73 excludes from compensation.

  1. AThe principal sum together with interest up to the day of payment, but not the ruin lossCorrect
  2. BThe principal sum and her entire loss from being ruined
  3. COnly the interest, without the principal
  4. DNothing more than the principal, without interest

Explanation

Illustration (n) to Section 73 states that A is not liable for anything except the principal sum together with interest up to the day of payment. Ruin is remote and indirect loss, so option B is wrong.

Did you get it right without looking?