CMA Intermediate · Management Accounting · Responsibility Accounting
Division P of Sundaram Ltd produces a component at variable cost Rs 120 per unit and can sell all output externally at Rs 180. It is operating at full capacity. Division Q can buy the same component externally at Rs 175. Under the general rule (marginal cost plus opportunity cost), what is the minimum transfer price and should P transfer internally?
Minimum transfer price is Rs 180, being variable cost Rs 120 plus the Rs 60 contribution lost on external sale. Since Q can buy externally at Rs 175, below this minimum, the company is better off not transferring internally.
- ARs 120; transfer internally
- BRs 175; transfer internally
- CRs 180; do not transfer internally since Q can buy at Rs 175Correct
- DRs 60; transfer internally
Explanation
At full capacity opportunity cost is the lost contribution 180-120 = Rs 60. Minimum price = 120 + 60 = Rs 180. Q can buy at Rs 175, which is less than P's minimum, so internal transfer is not beneficial to the company.
Did you get it right without looking?
One question tells you little. A timed set on Responsibility Accounting shows your real accuracy, how long you take and where you lose marks.
More Responsibility Accounting questions
- Division R of Bharat Components has capital employed of ₹80,00,000 and a required return of 15%. Its residual income is ₹4,00,000. What is t…
- Division X makes 10,000 units a year at full capacity, with variable cost Rs 50 and external price Rs 90. Division Y needs 4,000 units, and …
- Kaveri Ltd's Division P has capital employed of ₹50,00,000 and operating profit of ₹9,00,000. The company's cost of capital is 12%. What is …
- Division X of Sagar Foods has ROI of 22% and a manager is considering a project with ROI of 18%. The company's cost of capital is 14%. If th…
- A divisional manager of Kaveri Foods Ltd. incurred the following costs in a month: direct materials Rs 4,00,000, direct labour Rs 2,50,000, …
- A division of Kaveri Auto Ltd reports: sales Rs 20,00,000; variable costs Rs 11,00,000; controllable fixed costs Rs 3,00,000; non-controllab…