ACCA Applied Knowledge · Management Accounting · Performance measurement - application
Division R earns ROI of 20% on capital employed of $500,000. The cost of capital is 12%. A new project costing $100,000 would earn annual profit of $15,000. Which statement is correct?
The project earns 15%, lower than the division's 20% ROI, so an ROI-driven manager would reject it. However it exceeds the 12% cost of capital, adding $3,000 of residual income, so an RI-driven manager would accept it. This shows goal congruence differences.
- AThe manager using ROI would reject the project but the manager using RI would accept itCorrect
- BBoth ROI and RI would lead to acceptance
- CBoth ROI and RI would lead to rejection
- DThe manager using ROI would accept it but RI would reject it
Explanation
The project's return is 15%, below the existing 20%, so ROI would fall and the project be rejected. Its return exceeds the 12% cost of capital: RI change = 15,000 - 12,000 = +3,000, so RI favours acceptance. This shows how ROI can cause dysfunctional decisions.
Did you get it right without looking?
One question tells you little. A timed set on Performance measurement - application shows your real accuracy, how long you take and where you lose marks.
More Performance measurement - application questions
- Kestrel Ltd reported revenue of $800,000, cost of sales of $520,000 and operating expenses of $140,000. What is its operating profit margin?
- Division X has operating profit of $240,000 and capital employed of $1,200,000. The company's cost of capital is 15%. A new project would co…
- In the performance pyramid (Lynch and Cross), which pair is correctly identified as the top-level and the bottom-level aspects of the pyrami…
- A company uses the balanced scorecard. It measures 'percentage of customers who rate delivery as on time' and 'customer retention rate'. Whi…
- Division X of Brae Co has ROI of 20% and is considering a project costing $500,000 that would earn an annual profit of $90,000. The company'…
- A school's budget for the year was $1,200,000 for 800 pupils. Actual spending was $1,260,000 for 840 pupils, and the pass rate in national e…