ACCA Applied Knowledge · Management Accounting · Behavioural aspects of budgeting
Dunmore Co is considering the target level for next year's budget. Research suggests performance is highest when targets are set at a level that is challenging but achievable. Which of the following statements about target difficulty is correct?
Attainable standards needing reasonable effort tend to motivate better than ideal standards. Ideal standards assume perfect efficiency and normally produce persistent adverse variances, which demotivate staff. Very easy targets encourage complacency and slack, so the best level is challenging but achievable.
- AIdeal standards that assume perfect efficiency generally maximise motivation because they stretch staff most
- BVery easy targets maximise performance because staff always achieve them
- CAttainable standards that need reasonable effort tend to motivate better than ideal standardsCorrect
- DTarget difficulty has no effect on motivation if rewards are paid
Explanation
Attainable standards, which allow for normal losses and need reasonable effort, are seen as achievable and so tend to motivate. Ideal standards usually produce constant adverse variances and demotivate. Very easy targets encourage slack and complacency, and difficulty does affect motivation even when rewards exist.
Did you get it right without looking?
One question tells you little. A timed set on Behavioural aspects of budgeting shows your real accuracy, how long you take and where you lose marks.
More Behavioural aspects of budgeting questions
- A cost centre manager at Brindle Co has a controllable budget of $200,000 and actual controllable costs of $212,000. Allocated head office c…
- A sales manager is told that her budget target for the coming year is deliberately set at a level that is achievable by only a small number …
- Which situation would make an imposed budgeting approach more appropriate than a participative one?
- A budget is set at a level the manager believes is impossible to achieve. Which is the most likely behavioural consequence?
- Under a participative budgeting system, a manager expects to sell 10,000 units but submits a sales budget of 8,000 units so that the target …
- According to research on target-setting and motivation, which budget target is most likely to produce the best performance from a manager?