Skip to content

ACCA Strategic Professional · Advanced Audit and Assurance (International) · Quality management (firm and engagement level)

During a firm's cold file review of a completed audit, the reviewer finds that audit documentation was assembled into the final file six months after the audit report date. What is the main concern under ISA 230 and ISQM 1 requirements?

The concern is that the audit file was not assembled on a timely basis. ISA 230 requires assembly after the report date within a time limit set by firm policy, normally not exceeding 60 days. Six months exceeds that, indicating a quality weakness that the cold file review should report.

  1. AThe file must be assembled within a timely period, normally not more than 60 days after the report date, so late assembly breaches the firm's expected time limitCorrect
  2. BThere is no concern, because assembly of the file is flexible if the report was signed
  3. CThe audit report must be withdrawn and reissued to clients
  4. DThe firm must delete working papers created after the report date

Explanation

ISA 230 requires the auditor to assemble the final audit file on a timely basis after the date of the auditor's report, and the firm's policy typically sets a limit not exceeding 60 days. Six months is a breach. There is no requirement to withdraw the report, and documents must not be deleted after assembly.

Did you get it right without looking?

One question tells you little. A timed set on Quality management (firm and engagement level) shows your real accuracy, how long you take and where you lose marks.

More Quality management (firm and engagement level) questions