FRM Part II · FRM Exam Part II · Capital Planning at Large Bank Holding Companies: Supervisory Expectations and Range of Current Practice
During a review of a large bank holding company's capital planning, examiners find that loss estimates for the stress scenario are produced by separate business lines using different assumptions, with no central challenge or reconciliation. Which supervisory concern is most relevant?
The main concern is weak aggregation and governance. Capital planning should use consistent enterprise-wide assumptions with central, independent challenge. When business lines use different assumptions and nobody reconciles them, the resulting loss estimates are unreliable and the board cannot trust the overall capital adequacy conclusion.
- AWeak aggregation and governance of the capital planning process, leading to inconsistent and unchallenged estimatesCorrect
- BCapital distributions being too conservative
- CExcessive use of external credit ratings in the process
- DInsufficient dividend payments to shareholders
Explanation
Sound practice requires a consistent, enterprise-wide process with independent review and challenge of assumptions. Fragmented estimates with no reconciliation show weak governance and aggregation. Conservative distributions or dividend levels are not the issue described.
Did you get it right without looking?
One question tells you little. A timed set on Capital Planning at Large Bank Holding Companies: Supervisory Expectations and Range of Current Practice shows your real accuracy, how long you take and where you lose marks.
More Capital Planning at Large Bank Holding Companies: Supervisory Expectations and Range of Current Practice questions
- A bank's capital planning relies on loss estimates from a vendor model. Management documents that the model was validated, but the validatio…
- During a review of a BHC's capital planning, supervisors find that stress test results for the loan book rely on a loss model calibrated onl…
- A large bank holding company is designing the risk identification step of its capital planning process. Which approach best reflects supervi…
- A supervisor finds that a bank's capital plan is approved by the board with only a one-page summary, and that the board did not review key a…
- A bank estimates loan losses for a commercial portfolio using loss = PD × LGD × EAD. Under a stress scenario, the portfolio EAD is USD 400 m…
- A large bank holding company is building the risk identification step of its capital planning process. According to supervisory expectations…