Ferro Co has a labour budget of 12,000 hours for a month. Employees work a 160-hour month each, but 5% of the time paid is lost to idle time and no overtime is worked. What is the minimum number of employees needed to deliver the budgeted productive hours?
At least 79 employees are needed. Each employee gives 152 productive hours after 5% idle time, and 12,000 divided by 152 is about 78.9, which must be rounded up to 79 whole employees. Ignoring idle time gives only 75.
- A75 employees
- B79 employeesCorrect
- C72 employees
- D80 employees
Explanation
Productive hours per employee = 160 x 95% = 152. Employees needed = 12,000 / 152 = 78.9, so 79 employees are needed. 75 ignores idle time, and 72 deducts idle time the wrong way.
Did you get it right without looking?
One question tells you little. A timed set on Budget preparation shows your real accuracy, how long you take and where you lose marks.
More Budget preparation questions
- In the budget preparation process, the principal budget factor (limiting factor) should be identified early because it:
- Hartley Ltd uses incremental budgeting. Last year's actual overhead was $400,000, which included a one-off cost of $25,000. Next year, gener…
- Which of the following is an advantage of participative budgeting?
- Tarn Co budgets sales of 2,000 units of a product. A 90% learning curve applies, and the first unit takes 100 hours. Which statement about t…
- Delta Ltd makes a single product. Budgeted sales are 8,000 units. Opening inventory is 1,200 units and closing inventory is planned at 2,000…
- A company makes products X and Y. Machine hours are limited to 1,200 hours. X contributes $30 per unit and uses 2 machine hours per unit; Y …