CA Intermediate · Advanced Accounting · AS 16 Borrowing Costs
Ganga Power Ltd. is constructing a plant (qualifying asset) funded by a specific loan of Rs 80,00,000 at 10% p.a. Construction began on 1 April. Because of a labour strike, active development was suspended from 1 July to 30 September (extended period, not a necessary part of the process). Work resumed on 1 October and continued until 31 March. Further, from 1 January to 31 January a monsoon-related delay was a necessary part of the process in that location. What borrowing cost is capitalised for the year, and what is charged to profit and loss?
This option set contains an error in the key; the correct computation gives capitalised Rs 6,00,000 and charged Rs 2,00,000, since only the three-month strike suspension is expensed and the necessary monsoon delay stays capitalised.
- ACapitalised Rs 8,00,000; charged Rs nil
- BCapitalised Rs 5,33,333 ; charged Rs 2,66,667
- CCapitalised Rs 6,00,000; charged Rs 2,00,000
- DCapitalised Rs 6,66,667; charged Rs 1,33,333Correct
Explanation
Annual interest = 8,00,000, i.e. 66,667 per month. The strike suspension of 3 months (July-September) is extended, so Rs 2,00,000 is expensed. The January delay is a necessary part of the process, so it continues to be capitalised. Capitalised = 9 months x 66,667 = 6,00,000 plus... recheck: 12 months less 3 = 9 months = 6,00,000.
Did you get it right without looking?
One question tells you little. A timed set on AS 16 Borrowing Costs shows your real accuracy, how long you take and where you lose marks.
More AS 16 Borrowing Costs questions
- Sundaram Textiles Ltd. borrowed Rs 2,00,000 at 12% p.a. on 1 April to buy a machine for its own use. Which of the following items is NOT a b…
- Himalaya Steels Ltd borrowed ₹600 lakh at 10% p.a. on 1 April 2025 specifically to build a rolling mill, a qualifying asset. Active developm…
- Godavari Pharma Ltd. is constructing a manufacturing plant that is a qualifying asset. Construction of the plant was completed and the asset…
- Kaveri Textiles Ltd took a loan of USD 1,00,000 on 1 April to construct a new dyeing unit, a qualifying asset that remained under constructi…
- Vihaan Builders Ltd. has no specific borrowing for a plant under construction. During the year it had two general borrowings: Rs 40,00,000 a…
- Gupta Developers Ltd is constructing a residential complex of three towers with a specific loan. Tower A has been completed and is ready for…