Skip to content

CMA Foundation · Fundamentals of Financial and Cost Accounting · Cost, Cost Centre, Cost Unit and Cost Drivers

Ganga Textiles incurred Rs 4,00,000 on materials, Rs 2,50,000 on direct wages and Rs 50,000 on direct expenses for a job. Factory overhead is absorbed at 40% of direct wages and office overhead at 10% of factory cost. What is the total cost of the job?

The total cost of the job is Rs 8,80,000. Prime cost of Rs 7,00,000 plus factory overhead of Rs 1,00,000 gives factory cost of Rs 8,00,000. Adding office overhead of 10% of factory cost, Rs 80,000, gives the total cost.

  1. ARs 8,25,000
  2. BRs 8,80,000Correct
  3. CRs 8,50,000
  4. DRs 9,25,000

Explanation

Prime cost = 4,00,000+2,50,000+50,000 = 7,00,000. Factory overhead = 40% of 2,50,000 = 1,00,000, so factory cost = 8,00,000. Office overhead = 10% of 8,00,000 = 80,000. Total cost = 8,80,000. Taking office overhead on prime cost gives a different, wrong figure.

Did you get it right without looking?

One question tells you little. A timed set on Cost, Cost Centre, Cost Unit and Cost Drivers shows your real accuracy, how long you take and where you lose marks.

More Cost, Cost Centre, Cost Unit and Cost Drivers questions