CS Professional · Compliance Management, Audit and Due Diligence · Peer Review and Quality Review
Ghosh & Partners finishes the audit of Anand Pharma Ltd, a listed entity, and the engagement partner signs the audit report on 10 May. The engagement quality control reviewer completes the review on 14 May. What is the position under SQC 1?
This is not acceptable. SQC 1 requires the engagement quality control review to be completed before the report is issued. The review ended four days after the report was signed, so the timing requirement was not met whatever the reviewer concluded.
- AAcceptable, since the review was completed within a week of the report
- BAcceptable, provided the reviewer had no unresolved matters
- CNot acceptable, because the review must be completed before the report is issuedCorrect
- DAcceptable, because listed entity audits only need review before the annual general meeting
Explanation
SQC 1 requires the firm's policies to require completion of the engagement quality control review before the report is issued. Here the report was issued on 10 May and the review finished on 14 May, so the timing requirement was breached. Absence of unresolved matters does not cure the timing.
Did you get it right without looking?
One question tells you little. A timed set on Peer Review and Quality Review shows your real accuracy, how long you take and where you lose marks.
More Peer Review and Quality Review questions
- After an engagement quality control review of Yamuna Steels Ltd, the reviewer Karan notes that one significant judgment on asset impairment …
- Rao & Partners reviewed the file of Himalaya Agro Ltd (unlisted). The firm's criteria for engagement quality control review include public i…
- Reviewer Anita is performing an engagement quality control review for Narmada Infra Ltd. Which of the following best describes what the revi…
- For an audit of Bharat Steels Ltd, a reviewer discusses matters with the engagement partner and reviews the financial statements and draft r…
- At Iyer & Associates, partner Kavita Iyer leads the audit of a listed manufacturer. She proposes that her close colleague Ramesh be the enga…
- For a listed client's audit, reviewer Kabir Nair wants to prepare the documentation of his engagement quality control review. Which of the f…