CA Intermediate · Advanced Accounting · AS 10 Property, Plant and Equipment
Godavari Steel Ltd revalued its entire class of plant on 31 March 2025. Plant had cost Rs 20,00,000 with accumulated depreciation Rs 8,00,000 and was revalued at Rs 15,00,000. For the year 2025-26 the remaining life is 5 years, straight line, nil residual value. The company transfers nothing from revaluation reserve to retained earnings except as permitted. What is the depreciation charged for 2025-26 in the statement of profit and loss and the revaluation surplus created?
Depreciation is Rs 3,00,000 and the revaluation surplus is Rs 3,00,000. Book value was Rs 12,00,000, so the revaluation to Rs 15,00,000 creates a Rs 3,00,000 surplus. Depreciation is then charged on the revalued amount of Rs 15,00,000 over the remaining five years.
- ADepreciation Rs 3,00,000; surplus Rs 3,00,000Correct
- BDepreciation Rs 2,40,000; surplus Rs 3,00,000
- CDepreciation Rs 3,00,000; surplus Rs 7,00,000
- DDepreciation Rs 4,00,000; surplus Rs 3,00,000
Explanation
Book value = 20,00,000 - 8,00,000 = 12,00,000. Revalued at 15,00,000, so surplus = 3,00,000. Depreciation is on the revalued amount over remaining life: 15,00,000/5 = 3,00,000. The 2,40,000 option uses old book value 12,00,000/5.
Did you get it right without looking?
One question tells you little. A timed set on AS 10 Property, Plant and Equipment shows your real accuracy, how long you take and where you lose marks.
More AS 10 Property, Plant and Equipment questions
- Narmada Industries Ltd. revalues its plant on 31 March 2026. Cost Rs 50,00,000, accumulated depreciation Rs 20,00,000 (carrying amount Rs 30…
- Kaveri Industries Ltd. acquired a plant on 1 April 2023 for Rs 10,00,000 with a useful life of 10 years and nil residual value (straight lin…
- Kaveri Textiles Ltd owns a plant bought at ₹20,00,000 with accumulated depreciation of ₹8,00,000, so the carrying amount is ₹12,00,000. The …
- Narmada Foods Ltd bought a machine on 1 April 2021 for ₹10,00,000 and depreciates it at 10% per annum on original cost (straight line) with …
- Rudra Steels Ltd began constructing a furnace on 1 April 2025. Costs: materials Rs 30,00,000, labour Rs 10,00,000, and Rs 2,00,000 of abnorm…
- Sagar Packaging Ltd. bought a machine on 1 April 2021 for ₹20,00,000, including a motor of ₹2,00,000 that is depreciated separately. Both ha…