ACCA Strategic Professional · Strategic Business Leader · Cost and management accounting
Harbour Components plc is deciding whether to continue making a part in-house. The finance director lists the annual rent of the factory, which will be payable whether or not the part is made, as part of the cost of the part. Which cost classification best describes the rent for this decision, and what does it imply?
The rent is a fixed cost that will be incurred whatever the decision, so it is not incremental and is irrelevant. It should be excluded when comparing making with buying in, because only costs that differ between the alternatives affect the decision.
- AIt is an irrelevant (non-incremental) fixed cost for this decision, so it should be excluded from the comparison with buying inCorrect
- BIt is a relevant variable cost, so it should be included in full in the comparison with buying in
- CIt is an opportunity cost, so it should be added to the purchase price of the bought-in part
- DIt is a sunk cost only if the lease was signed in a previous year, so it must always be included
Explanation
Rent payable regardless of the decision does not change with the choice, so it is not an incremental cash flow and is irrelevant. Including it (option B) would overstate the benefit of buying in. Rent is not an opportunity cost unless the space has an alternative use.
Did you get it right without looking?
One question tells you little. A timed set on Cost and management accounting shows your real accuracy, how long you take and where you lose marks.
More Cost and management accounting questions
- Zenith Retail's management accountant says that the cost of a market research report commissioned last quarter for $60,000, which is non-ref…
- Kestrel Components makes precision parts. Its management accountant allocates overheads using a single rate per machine hour. Product A, a h…
- Marlow Ltd's standard labour rate is $12 per hour, with 3 hours per unit. In a month it produced 2,000 units, paid for 6,400 hours at $12.50…
- Brightwater Engineering is deciding whether to accept a one-off order using spare capacity. Management debates the following costs: (1) $60,…
- Corvane Logistics sets its annual budget by taking last year's actual costs for each department and adding 3% for inflation. Department head…
- Kestrel Components budgeted to buy 10,000 kg of material at $5.00 per kg for production of 5,000 units (2 kg per unit). Actual production wa…