Hard: Under the Cost Accounting Standard on Pollution Control Cost (CAS 16 is Environmental Cost, CAS 17 is Research and Development), which treatment of research and development cost is consistent with CAS 17? A firm spent Rs 8,00,000 on a development project that is expected to benefit five years of output and Rs 2,00,000 on basic research. Assuming the development cost is amortised on a straight line basis from the first year, the amount charged to cost for year 1 (research plus amortisation) is:

Research cost of Rs 2,00,000 is charged to the period, while the development cost of Rs 8,00,000 is spread over five years at Rs 1,60,000 per year. The first year charge is therefore Rs 3,60,000.

  1. ARs 2,00,000
  2. BRs 3,60,000Correct
  3. CRs 10,00,000
  4. DRs 1,60,000

Explanation

Research cost of Rs 2,00,000 is charged in the period. Development cost of Rs 8,00,000 over 5 years gives Rs 1,60,000 per year. Total charge for year 1 = 2,00,000 + 1,60,000 = 3,60,000. Rs 10,00,000 expenses everything immediately; Rs 1,60,000 omits the research cost.

Did you get it right without looking?

One question tells you little. A timed set on Cost Accounting Standards (CAS 1 to CAS 24) shows your real accuracy, how long you take and where you lose marks.

More Cost Accounting Standards (CAS 1 to CAS 24) questions