CMA Foundation · Fundamentals of Financial and Cost Accounting · Statement of Cost and Profit (Cost Sheet)
In a cost sheet, which of the following is obtained by adding factory overheads to prime cost and adjusting for opening and closing work-in-progress?
Factory (works) cost is the figure obtained by adding factory overheads to prime cost and adjusting for opening and closing work-in-progress. Administration overheads are added after this stage to arrive at cost of production, followed by stock adjustments for finished goods to reach cost of goods sold.
- ACost of production
- BFactory (works) costCorrect
- CCost of goods sold
- DCost of sales
Explanation
Prime cost plus factory overheads gives gross factory cost. Adjusting for the opening and closing work-in-progress gives factory or works cost. Office and administration overheads are added only after this stage to reach cost of production, so cost of production is not correct.
Did you get it right without looking?
One question tells you little. A timed set on Statement of Cost and Profit (Cost Sheet) shows your real accuracy, how long you take and where you lose marks.
More Statement of Cost and Profit (Cost Sheet) questions
- Which of the following items is excluded from a cost sheet because it is a financial item and not a part of cost of production or sales?
- Kapoor Industries had raw material opening stock Rs 30,000, purchases Rs 2,10,000, carriage inwards Rs 10,000 and closing stock Rs 40,000. D…
- Mehta Textiles has a cost of sales of ₹2,40,000 for a job and wants a selling price that gives a profit of 20% on selling price. What is the…
- Sharma Tools Ltd has a total cost of sales of Rs 4,80,000 for the period. It sells goods at a price that gives a profit of 20% on selling pr…
- Vikram Engineering has prime cost Rs 5,00,000, factory overheads Rs 1,50,000, opening work-in-progress Rs 40,000 and closing work-in-progres…
- Gupta Plastics puts 5,000 kg of material into a process costing Rs 2,00,000 in total. Normal waste is 10% of input with no realisable value.…