CMA Intermediate · Operations Management and Strategic Management · Optimum Allocation of Resources - LPP
In a maximisation simplex table, a variable has a positive Cj − Zj, but every coefficient in its column in the constraint rows is zero or negative. What does this indicate?
It indicates an unbounded solution. A positive Cj − Zj means the objective can still improve by increasing that variable, but with no positive column coefficients the ratio test imposes no limit. The variable can grow indefinitely, so the objective has no finite maximum.
- AThe problem has an unbounded solutionCorrect
- BThe problem has multiple optimal solutions
- CThe problem is infeasible
- DThe current solution is degenerate and optimal
Explanation
A positive Cj − Zj means increasing the variable raises the objective. If no row has a positive coefficient, the minimum ratio test has no limit, so the variable can increase indefinitely without violating any constraint. This signals an unbounded solution. Multiple optima would show a zero Cj − Zj for a non-basic variable at optimality instead.
Did you get it right without looking?
One question tells you little. A timed set on Optimum Allocation of Resources - LPP shows your real accuracy, how long you take and where you lose marks.
More Optimum Allocation of Resources - LPP questions
- In converting a maximisation LPP with all constraints of the '≤' type into the standard form for the simplex method, what is added to each c…
- A firm maximises profit subject to the constraints x + y <= 4 and x + y >= 9, with x, y >= 0. What does the graphical method show?
- In the graphical method of solving a two-variable linear programming problem, the set of all points that satisfy every constraint, including…
- Maximise Z = 40x1 + 30x2 subject to x1 + x2 ≤ 80, 2x1 + x2 ≤ 100, x1, x2 ≥ 0, using the simplex method. What is the optimal value of Z?
- In a linear programming model, which of the following is an example of a non-negativity restriction?
- Sundaram Metals maximises profit Z = 5x + 4y subject to: 6x + 4y ≤ 24 (machine hours) and x + 2y ≤ 6 (labour hours), x, y ≥ 0. The optimal s…