CS Professional · Insolvency and Bankruptcy - Law and Practice · Corporate Insolvency Resolution Process
In a pre-packaged insolvency resolution process, the committee of creditors has approved the resolution plan under section 54K. Which statement about the Adjudicating Authority's handling under section 54L is correct?
Under section 54L, the Adjudicating Authority approves a pre-packaged plan within thirty days of receipt if it is satisfied the plan meets section 30(2) requirements, and it must first check that the plan has provisions for effective implementation. It can reject a non-conforming plan.
- AIt may approve the plan within thirty days of receipt if satisfied it meets section 30(2) requirements, after satisfying itself that the plan has provisions for effective implementationCorrect
- BIt must approve the plan within seven days of receipt without examining implementation provisions
- CIt may approve the plan at any time, as no time limit applies in pre-packs
- DIt must approve any plan approved by the committee of creditors, as it has no power to reject it
Explanation
Section 54L(1) requires the Adjudicating Authority, if satisfied that the plan meets section 30(2) requirements, to approve it within thirty days of receipt, and the proviso requires it first to satisfy itself that the plan has provisions for effective implementation. Section 54L(3) also allows rejection if the plan does not conform, so it is not bound to approve every plan.
Did you get it right without looking?
One question tells you little. A timed set on Corporate Insolvency Resolution Process shows your real accuracy, how long you take and where you lose marks.
More Corporate Insolvency Resolution Process questions
- In a fast track process for Kaveri Textiles Ltd, the resolution professional finds that the resolution plan cannot be finalised within ninet…
- Vihaan Traders Pvt Ltd failed to pay a debt due on 10 January 2020. Another default by it occurred on 15 June 2020, within the period of sus…
- Ganga Polymers Ltd files a section 10 application proposing CA Rohit Menon as interim resolution professional. The application is otherwise …
- An insolvency professional, CS Rohan Iyer, was approved by unrelated financial creditors under section 54A(2)(e) as the proposed resolution …
- Under a pre-packaged insolvency resolution process for Arjun Foods Ltd, the committee of creditors, before approval of the resolution plan, …
- The CIRP period of Deccan Polymers Ltd expires while the resolution plan awaits the Adjudicating Authority's decision. The RP asks whether h…