In a Pune factory, Machine A makes 60% of the output and Machine B makes the remaining 40%. Of A's items 5% are defective, and of B's items 10% are defective. An item picked at random is found defective. What is the probability that it came from Machine A?
The probability is 3/7. Machine A contributes 0.03 of defective items (0.6 x 0.05) and Machine B contributes 0.04 (0.4 x 0.10), so the total defective proportion is 0.07. Dividing A's share by the total gives 0.03/0.07 = 3/7 by Bayes' theorem.
- A3/7Correct
- B4/7
- C3/5
- D1/2
Explanation
P(A and defective) = 0.6 x 0.05 = 0.03 and P(B and defective) = 0.4 x 0.10 = 0.04. Total P(defective) = 0.07. P(A | defective) = 0.03/0.07 = 3/7. The option 4/7 is the probability for Machine B, and 3/5 is just the prior share of A.
Did you get it right without looking?
One question tells you little. A timed set on Probability shows your real accuracy, how long you take and where you lose marks.
More Probability questions
- The odds in favour of a Mumbai firm winning a tender are 3 to 5. What is the probability that the firm does not win the tender?
- A Chennai firm buys components from three suppliers X, Y and Z, who provide 50%, 30% and 20% of the supply, with defective rates of 2%, 3% a…
- A bag has 4 red and 6 green balls. Two balls are drawn one after another without replacement. What is the probability that both are green?
- A fair coin is tossed 3 times. Let X be the number of heads. What is E(X) and E(X²)?
- A box at a Pune warehouse holds 6 defective and 4 good bulbs. Two bulbs are drawn one after another without replacement. What is the probabi…
- Ramesh Traders in Surat launches a product. Profit is Rs 50,000 with probability 0.3, Rs 20,000 with probability 0.5, and a loss of Rs 30,00…