CMA Foundation · Fundamentals of Financial and Cost Accounting · Statement of Cost and Profit (Cost Sheet)
In a standard cost sheet, which of the following is obtained by adding factory overheads to prime cost?
Works cost, also called factory cost, is obtained by adding factory overheads to prime cost. Cost of production comes later, after administration overheads are added to works cost, and the total cost follows only after selling and distribution overheads are included.
- AWorks costCorrect
- BCost of production
- CCost of goods sold
- DTotal cost
Explanation
Prime cost plus factory (works) overheads gives works (factory) cost. Cost of production is reached only after adding administration overheads to works cost, so that option is premature.
Did you get it right without looking?
One question tells you little. A timed set on Statement of Cost and Profit (Cost Sheet) shows your real accuracy, how long you take and where you lose marks.
More Statement of Cost and Profit (Cost Sheet) questions
- Mehta Constructions is quoting for a job with total cost of Rs 2,50,000. It wants a profit equal to 25% on cost. What is the tender price?
- Sharma Tools Ltd has a total cost of sales of Rs 4,80,000 for the period. It sells goods at a price that gives a profit of 20% on selling pr…
- Sharma Plastics has normal scrap arising from a process, and the scrap realises Rs 8,000 when sold. The scrap is not identifiable with any p…
- In a cost sheet, which of the following is classified as part of prime cost?
- Vikram Engineering has prime cost Rs 5,00,000, factory overheads Rs 1,50,000, opening work-in-progress Rs 40,000 and closing work-in-progres…
- Gupta Plastics puts 5,000 kg of material into a process costing Rs 2,00,000 in total. Normal waste is 10% of input with no realisable value.…