CA Intermediate · Cost and Management Accounting · Unit & Batch Costing
In batch costing, if a batch of 1,000 units is completed and 40 units are found defective, which are reworked at a cost attributable to a specific customer's special requirements, how is the rework cost treated?
The rework cost is charged to that specific batch or job, because it arises from the special requirements of that particular order. Only rework caused by general, normal factors is spread across production as factory overhead.
- ACharged to that specific batch or jobCorrect
- BSpread over all factory output as normal overhead
- CCredited to the costing profit and loss account
- DIgnored until the units are sold
Explanation
Rework cost caused by the special requirements of a particular order is charged directly to that job or batch. Rework due to normal, general causes is treated as factory overhead.
Did you get it right without looking?
One question tells you little. A timed set on Unit & Batch Costing shows your real accuracy, how long you take and where you lose marks.
More Unit & Batch Costing questions
- Kaveri Components makes a batch of 1,000 units. Batch cost is Rs 2,40,000. Normal spoilage of 50 units is sold as scrap at Rs 40 each, with …
- A firm makes Product Z in batches of 500 units. Per batch: material Rs 60,000, labour Rs 25,000, and set-up cost Rs 5,000. Factory overheads…
- In batch costing, the cost per unit of a batch is obtained by:
- Which of the following is a feature of batch costing that distinguishes it from unit costing?
- Verma Engineering completes a batch of 800 units at a total cost of ₹4,00,000. It sells the batch at a profit of 25% on selling price. What …
- Kapoor Components makes a part in batches. Each batch has a set-up cost of ₹3,000, and the carrying cost is ₹4 per unit per year. Annual dem…