In cost classification, a cost is called controllable when:
A cost is controllable when the manager in charge of a cost centre can influence its amount through their own decisions within a given period. Behaviour with output, traceability to units or one-time occurrence describe other classifications, not controllability.
- AIt can be influenced by the decision of the manager responsible for the cost centre within a given periodCorrect
- BIt varies in direct proportion to the level of output
- CIt can be traced to a single cost unit economically
- DIt is incurred only once in the life of a project
Explanation
A controllable cost is one whose amount a specified manager can influence by their own action in the relevant period. Variability with output relates to variable cost, traceability relates to direct cost, and one-time incurrence has no link to controllability. So the first option is the only correct one.
Did you get it right without looking?
One question tells you little. A timed set on Classification of Costs (CAS 1) shows your real accuracy, how long you take and where you lose marks.
More Classification of Costs (CAS 1) questions
- A factory of Sundaram Textiles in Coimbatore incurred a semi-variable maintenance cost of ₹58,000 at 4,000 machine hours and ₹70,000 at 6,00…
- A telephone bill of Anjali Traders consists of a fixed line rental of ₹900 per month plus ₹2 per call. How should this cost be classified, a…
- Which of the following is correctly classified as a direct expense rather than an overhead for a particular job?
- Sharma Textiles has a spinning department. For its manager, which of the following is most clearly a non-controllable cost?
- Which of the following would be treated as a normal cost rather than an abnormal cost in a manufacturing unit?
- In a manufacturing firm, the salary of the factory production manager and the salary of the sales manager are classified, by function, respe…