ACCA Strategic Professional · Advanced Financial Management · Impact of financing on investment decisions and adjusted present values
In the adjusted present value (APV) method, at which rate are the project's base-case operating cash flows normally discounted?
Base-case cash flows in APV are discounted at the ungeared cost of equity, which reflects the project's business risk as if all-equity financed. Financing side effects are added separately, so using the WACC would double count the effects of gearing.
- AThe ungeared (all-equity) cost of equity reflecting the project's business riskCorrect
- BThe company's existing weighted average cost of capital
- CThe after-tax cost of debt
- DThe risk-free rate
Explanation
APV first values the project as if it were financed wholly by equity, so the operating cash flows are discounted at the ungeared cost of equity for the project's business risk. Financing side effects such as tax shields and issue costs are valued separately. Using the existing WACC would mix financing effects into the base case and double count them.
Did you get it right without looking?
One question tells you little. A timed set on Impact of financing on investment decisions and adjusted present values shows your real accuracy, how long you take and where you lose marks.
More Impact of financing on investment decisions and adjusted present values questions
- Which statement best describes why an APV analysis of a project in a new business sector should use an ungeared cost of equity derived from …
- Brenn Co raises $4m of perpetual debt to finance a project, but the project's debt capacity is assessed at only $3m. The tax rate is 30%, an…
- Nyala Ltd is an all-equity project-financed company with an equity beta of 1.20. Risk-free rate is 4% and market return is 9%. Under the APV…
- A company uses APV to appraise a project financed by newly issued debt. Which of the following is a financing side effect that should be inc…
- Corvin plc is appraising a project costing $6 million. Base-case NPV at the ungeared cost of equity is -$90,000. The project supports debt o…
- A company with a constant debt-to-equity ratio of 1:2 (by market value) has a geared cost of equity of 12%. Its pre-tax cost of debt is 5% a…