IAI Actuarial Core Principles · Risk Modelling and Survival Analysis · Applications of time series models
In the Box-Jenkins approach to fitting an ARIMA model to a time series, which sequence of stages is correct?
The correct order is to make the series stationary and identify a tentative model, estimate its parameters, check the residuals for white noise, and then forecast. Diagnostics must follow estimation, and forecasting is done only once the model is judged adequate.
- AEstimate parameters, identify a tentative model, check diagnostics, then difference the data
- BIdentify a tentative model after making the series stationary, estimate parameters, carry out diagnostic checks on the residuals, then forecastCorrect
- CForecast, estimate parameters, identify the model, then test the residuals
- DCheck the residuals, identify the model, estimate parameters, then make the series stationary
- Estimate parameters, forecast, then identify the model and difference the data
Explanation
Box-Jenkins begins by making the series stationary (e.g. differencing) and identifying a tentative ARIMA(p,d,q) from the ACF and PACF. Parameters are then estimated, residuals are checked for white noise, and only an adequate model is used to forecast. Options that put estimation or forecasting before identification reverse the logic.
Did you get it right without looking?
One question tells you little. A timed set on Applications of time series models shows your real accuracy, how long you take and where you lose marks.
More Applications of time series models questions
- An analyst fits an ARIMA model to monthly claim counts and finds the sample autocorrelation function of the raw series decays very slowly fr…
- For an AR(2) process X_t = 0.5 X_{t-1} + 0.2 X_{t-2} + e_t, the lag-1 autocorrelation rho_1 is obtained from the Yule-Walker equations. What…
- Consider the process Y_t = 1.5 Y_{t-1} - 0.5 Y_{t-2} + e_t, with e_t white noise. Which statement is correct?
- An ARMA model is fitted to a series of 200 observations and the residual autocorrelations at lags 1 to 10 are computed. A Ljung-Box (portman…
- An MA(1) process is X_t = e_t + 0.5 e_{t-1}, where e_t is white noise with variance 2. What is the autocorrelation at lag 1 and at lag 2?
- A time series follows the process X_t = 0.6 X_{t-1} + e_t, where e_t is white noise with variance 4. Which statement about this process is c…