CA Intermediate · Auditing and Ethics · Audit Strategy, Audit Planning and Audit Programme

Jain & Co. is the statutory auditor of Sunrise Engineering Ltd. During planning, the auditor sets overall materiality at ₹10 lakh and performance materiality at ₹7 lakh. Midway through the audit, the team learns that actual profit before tax is far lower than the expected figure used to compute materiality. Which response is correct under SA 320 (Materiality in Planning and Performing an Audit)?

The auditor should revise materiality for the financial statements as a whole and reconsider performance materiality and the further audit procedures. SA 320 requires revision when new information would have led to a different figure at the outset, and management's agreement is not required.

  1. ARetain the original materiality since it was fixed at the planning stage and cannot be changed
  2. BRevise materiality for the financial statements as a whole, and reconsider performance materiality and the nature, timing and extent of further audit proceduresCorrect
  3. CRevise only the performance materiality and leave overall materiality unchanged
  4. DRevise materiality only if management agrees in writing to the change

Explanation

SA 320 requires the auditor to revise materiality for the financial statements as a whole if information becomes available during the audit that would have led to a different figure initially. The auditor must then determine whether performance materiality needs revision and whether the nature, timing and extent of further audit procedures remain appropriate. Keeping the original figure or revising only performance materiality ignores this requirement, and management's consent is not needed.

Did you get it right without looking?

One question tells you little. A timed set on Audit Strategy, Audit Planning and Audit Programme shows your real accuracy, how long you take and where you lose marks.

More Audit Strategy, Audit Planning and Audit Programme questions