Kapoor Textiles has a standard cost of ₹85 per metre of cloth. In a month it produced 4,000 metres at an actual total cost of ₹3,56,000. A further 500 metres were estimated in a quotation at ₹90 per metre but not produced. Which statement is correct about the cost per metre for the 4,000 metres produced?

Actual cost per metre is ₹3,56,000 divided by 4,000, giving ₹89. Against the standard of ₹85 this is ₹4 higher. The ₹90 estimate concerns metres not produced, so it is not the benchmark here.

  1. AActual cost per metre is ₹89, which exceeds standard by ₹4Correct
  2. BActual cost per metre is ₹89, which is below the estimate by ₹1
  3. CActual cost per metre is ₹85, equal to standard
  4. DActual cost per metre is ₹90, exceeding standard by ₹5

Explanation

Actual cost per metre = 3,56,000 / 4,000 = ₹89. Standard is ₹85, so actual exceeds standard by ₹4. The ₹90 estimate relates to unproduced cloth and is irrelevant to the comparison; the 'below estimate' option misuses it.