Kapoor Textiles sets a standard of 5 labour hours per unit at ₹40 per hour. The standard time includes 10% of the paid time as normal idle time. What is the standard labour cost per unit if 5 hours is the productive (working) time required?
The standard labour cost is ₹222.22 per unit. Since normal idle time is 10% of paid time, productive time of 5 hours is 90% of paid hours, so paid hours are 5 divided by 0.9, about 5.556, at ₹40 per hour.
- A₹200.00
- B₹220.00
- C₹222.22Correct
- D₹180.00
Explanation
Idle time is 10% of paid time, so working time is 90% of paid time. Paid hours = 5/0.90 = 5.5556 hours. Cost = 5.5556 x 40 = ₹222.22. Adding 10% to 5 hours gives ₹220, which wrongly takes idle time as 10% of working time.
Did you get it right without looking?
One question tells you little. A timed set on Standard Costing and Variance Analysis shows your real accuracy, how long you take and where you lose marks.
More Standard Costing and Variance Analysis questions
- Gamma Fabrics Ltd budgets fixed overheads of ₹3,00,000 for 10,000 units. In the month, actual output was 9,000 units and actual fixed overhe…
- Under standard costing, the variable overhead expenditure variance is computed as the difference between:
- Standard labour mix for a batch at Coimbatore Pumps is 40 hours skilled at ₹50 and 60 hours unskilled at ₹30. Actual hours were 45 skilled a…
- Sundaram Fabrics set a standard price of Rs 40 per kg for a raw material. During the month it bought and used 500 kg at an actual price of R…
- Mehta Industries fixes the standard material cost for one unit of product as follows: gross input 12 kg at ₹50 per kg, with a normal loss of…
- For a month, the standard material cost of actual output was Rs 90,000 and the actual material cost was Rs 93,600. The material price varian…