CA Intermediate · Cost and Management Accounting · Activity Based Costing

Kaveri Appliances makes two products, X and Y. Traditional absorption uses direct labour hours, with total overhead of ₹6,00,000 and 30,000 labour hours in total (X: 10,000 hours; Y: 20,000 hours). Under ABC, the overhead splits into set-up cost ₹2,40,000 (driver: 60 set-ups; X: 40, Y: 20) and other overhead ₹3,60,000 (driver: labour hours). Production is X: 5,000 units and Y: 10,000 units. What is the overhead per unit of X under ABC, and how does it compare with traditional costing?

Under ABC, X bears ₹2,80,000 of overhead, i.e. ₹56 per unit, compared with ₹40 per unit under traditional costing.

  1. A₹56 per unit under ABC, against ₹40 traditionallyCorrect
  2. B₹64 per unit under ABC, against ₹20 traditionally
  3. C₹48 per unit under ABC, against ₹40 traditionally
  4. D₹80 per unit under ABC, against ₹40 traditionally

Explanation

Traditional rate = ₹6,00,000 / 30,000 hours = ₹20 per hour. X uses 10,000 hours, so it is absorbed ₹2,00,000, i.e. ₹2,00,000 / 5,000 = ₹40 per unit. ABC: set-up rate = ₹2,40,000 / 60 = ₹4,000 per set-up, so X gets 40 × 4,000 = ₹1,60,000. Other overhead rate = ₹3,60,000 / 30,000 = ₹12 per hour, so X gets 10,000 × 12 = ₹1,20,000. Total for X = ₹2,80,000; per unit = ₹2,80,000 / 5,000 = ₹56. ABC gives ₹56 per unit against ₹40 traditionally, so X was under-costed by the traditional method.