Kaveri Engineering Ltd, a registered supplier, provides consultancy services to Orion Pvt Ltd. Invoice was issued on 12 July 2026 for Rs 5,00,000 (excluding tax). The service was completed on 20 June 2026, and the invoice should have been issued within 30 days of completion. Payment was received on 5 August 2026. What is the time of supply of the service?

The time of supply is 12 July 2026. Because the invoice was issued within the 30-day period after completion of the service, time of supply is the earlier of the invoice date and the payment date. The invoice date of 12 July is earlier than the payment received on 5 August.

  1. A20 June 2026, being the date of completion
  2. B12 July 2026, being the date of invoiceCorrect
  3. C5 August 2026, being the date of payment
  4. D20 July 2026, being the last date for issuing the invoice

Explanation

For services, if the invoice is issued within the prescribed period (30 days from the date of supply), the time of supply is the earlier of the invoice date and the date of payment. Invoice was issued on 12 July, which is within 30 days of 20 June (deadline 20 July). Payment came later on 5 August. The earlier date is 12 July 2026.