Kaveri Engineering uses the Rowan plan. Standard time for a job is 50 hours, actual time taken is 40 hours, and the rate is Rs 80 per hour. What is the total earning of the worker for the job?
Under the Rowan plan the bonus is time saved divided by time allowed, multiplied by time taken and the hourly rate. Here that is 10/50 x 40 x 80 = Rs 640, which added to basic wages of Rs 3,200 gives total earnings of Rs 3,840.
- ARs 3,200
- BRs 3,840Correct
- CRs 3,520
- DRs 4,000
Explanation
Time saved = 10 hours. Basic wages = 40 x 80 = Rs 3,200. Rowan bonus = (time saved / time allowed) x time taken x rate = (10/50) x 40 x 80 = Rs 640. Total = Rs 3,840. Rs 3,520 results from wrongly using the Halsey 50% bonus (Rs 320), and Rs 4,000 pays for the full 50 standard hours.
Did you get it right without looking?
One question tells you little. A timed set on Employee Cost and Direct Expenses shows your real accuracy, how long you take and where you lose marks.
More Employee Cost and Direct Expenses questions
- Which of the following is treated as an idle time cost arising from a normal cause in cost accounting for employees?
- Kapoor Fabrics has a skilled workman who produces 120 units in a 50-hour week. The standard output is 2 units per hour. He is paid under the…
- Which of the following is treated as an employee cost that is NOT directly traceable to a specific cost unit, and is therefore normally clas…
- Mehta Plastics has an annual workforce of 400 workers at the start of the year; during the year 30 workers left, 20 were discharged, and 50 …
- Which of the following is treated as an indirect employee cost in a manufacturing company and therefore included in factory overheads?
- Under the Rowan plan, a worker has a time rate of Rs 30 per hour, standard time of 60 hours and actual time taken of 45 hours. What is the t…