CS Professional · Insolvency and Bankruptcy - Law and Practice · Corporate Insolvency Resolution Process
Kaveri Textiles Ltd, a company that has defaulted on a loan, passes a special resolution of its shareholders approving the filing of an application for initiating CIRP under section 10. It files the application with the Adjudicating Authority and names the resolution professional proposed to be appointed as interim resolution professional. The application is complete and no disciplinary proceeding is pending against the proposed professional. Within how many days of receipt must the Adjudicating Authority pass an order admitting or rejecting it?
The Adjudicating Authority must pass its order within fourteen days of receiving the corporate applicant's application under section 10. It admits the application if complete and no disciplinary proceeding is pending against the proposed professional, and rejects it if incomplete.
- ASeven days
- BFourteen daysCorrect
- CThirty days
- DForty-five days
Explanation
Under section 10(4), the Adjudicating Authority must, within fourteen days of receipt of the application, either admit it if complete (and no disciplinary proceeding is pending against the proposed resolution professional) or reject it if incomplete. Seven days is the period given to rectify defects after a notice, not the period for deciding.
Did you get it right without looking?
One question tells you little. A timed set on Corporate Insolvency Resolution Process shows your real accuracy, how long you take and where you lose marks.
More Corporate Insolvency Resolution Process questions
- Vihaan Traders Pvt Ltd failed to pay a debt due on 10 January 2020. Another default by it occurred on 15 June 2020, within the period of sus…
- Ganga Polymers Ltd files a section 10 application proposing CA Rohit Menon as interim resolution professional. The application is otherwise …
- Ganga Metals Ltd's fast track process was extended by the Adjudicating Authority by the maximum permissible further period. What is the long…
- An insolvency professional, CS Rohan Iyer, was approved by unrelated financial creditors under section 54A(2)(e) as the proposed resolution …
- Under a pre-packaged insolvency resolution process for Arjun Foods Ltd, the committee of creditors, before approval of the resolution plan, …
- The CIRP period of Deccan Polymers Ltd expires while the resolution plan awaits the Adjudicating Authority's decision. The RP asks whether h…