Skip to content

ACCA Strategic Professional · Advanced Audit and Assurance (International) · Other current issues

Kestrel Foods plc has a loan facility maturing three months after the date the auditor expects to sign the report. Management's going concern assessment covers only twelve months from the reporting date and shows adequate cash, assuming the facility is renewed, but no renewal has been agreed. Which action is most consistent with ISA 570 (Revised)?

The auditor should evaluate the likelihood and terms of the facility renewal and obtain evidence on management's plans, because the assumption is critical to the going concern assessment. Acceptance based on period length alone or an immediate adverse opinion would be inappropriate before evidence is gathered and uncertainty assessed.

  1. AAccept the assessment because the twelve-month period meets the minimum required by the standard
  2. BEvaluate the likelihood and terms of renewal, and obtain evidence on management's plans, since the assumption is critical to going concernCorrect
  3. CIssue an adverse opinion because the facility is not yet renewed
  4. DReport a key audit matter and take no further procedures

Explanation

ISA 570 requires the auditor to evaluate management's plans for future actions and whether they are feasible; an unconfirmed refinancing is a key assumption needing evidence. An adverse opinion is premature before evidence is obtained and a material uncertainty assessed. The twelve-month period is only a minimum under the framework and the standard asks the auditor to consider events beyond it.