ACCA Strategic Professional · Advanced Financial Management · Discounted cash flow techniques
Kestrel plc is appraising a project. It has already spent $120,000 on a feasibility study, and a further $30,000 of head-office overhead will be allocated to the project but would be incurred whether or not the project goes ahead. The project needs new machinery costing $400,000. Which amount is the relevant initial outlay for the appraisal?
The relevant initial outlay is $400,000. The feasibility study is a sunk cost and the head-office overhead would be incurred regardless, so neither is an incremental future cash flow. Only the machinery purchase changes because of the decision and belongs in the appraisal.
- A$400,000Correct
- B$430,000
- C$520,000
- D$550,000
Explanation
The feasibility study is a sunk cost and the allocated overhead is not incremental, so both are ignored. Only the $400,000 machinery cost is a relevant future incremental cash flow. Including the overhead ($430,000) or the study ($520,000 or $550,000) wrongly counts non-relevant costs.
Did you get it right without looking?
One question tells you little. A timed set on Discounted cash flow techniques shows your real accuracy, how long you take and where you lose marks.
More Discounted cash flow techniques questions
- Which statement about hard and soft capital rationing is correct?
- Zenith plc, an all-equity-financed software firm, is considering a project in the retail sector. Which approach to the discount rate is most…
- Which of the following is an example of hard capital rationing?
- A firm has an equity beta of 1.20 when geared with debt-to-equity of 1:3 by market value. Debt beta is zero and tax is 25%. Using the Modigl…
- Zeta plc has a single-period capital constraint of $500,000 available now. Projects are divisible and cannot be repeated. Project A: investm…
- Harbin plc has $100,000 available at time 0 only. The projects below are indivisible and cannot be repeated. X: outlay $60,000, NPV $14,000.…