ACCA Applied Skills · Performance Management · Make-or-buy and other short-term decisions
Kora Co has spare capacity issues: skilled labour is fully employed on normal work earning a contribution of $12 per labour hour after paying labour at $15 per hour. A special order needs 200 hours of this labour. No extra labour can be hired. What is the relevant cost of labour for the order?
The relevant cost is $5,400. Labour is fully employed, so the order costs the wage of $15 per hour plus the $12 per hour contribution lost from normal work. That is $27 per hour, and 200 hours gives $5,400.
- A$3,000
- B$2,400
- C$5,400Correct
- D$5,400 less the order's contribution
Explanation
With labour fully employed, the relevant cost is the wage plus the opportunity cost of lost contribution. That is $15 + $12 = $27 per hour, so 200 x $27 = $5,400. $3,000 ignores the lost contribution, and $2,400 ignores the wage.
Did you get it right without looking?
One question tells you little. A timed set on Make-or-buy and other short-term decisions shows your real accuracy, how long you take and where you lose marks.
More Make-or-buy and other short-term decisions questions
- Which statement about limiting factor analysis is correct?
- Harlow Co makes 4,000 units of part T. Relevant making cost is $22 per unit. A supplier offers T at $25 per unit. If Harlow buys, the freed …
- A firm needs 500 kg of material X for a special order. It holds 300 kg in inventory, bought at $8 per kg. The material is regularly used in …
- Brindle Co makes products X and Y using a scarce 10,000 machine hours. X: variable cost $12, machine time 2 hours, buy-in price $20 per unit…
- Marlow Co makes component K at a variable cost of $14 per unit and a fixed overhead absorption of $6 per unit. Fixed costs would continue un…
- Zeta Co makes three products, all in demand with no sales limits. Skilled labour is the only scarce resource. Contribution per unit: Product…