Lakshmi Pharma Ltd. sent raw materials to a job worker on 1 July 2024 under intimation. Because of a regulatory delay in plant approval, the job work could not be completed. Lakshmi showed sufficient cause to the Commissioner, who extended the period to the maximum permissible. By what date must the inputs be brought back or supplied from the job worker's place to avoid deemed supply?

The inputs must be returned or supplied by 1 July 2026. The basic limit for inputs is one year, and the Commissioner can extend it by at most one further year on sufficient cause, giving two years from the date of sending out.

  1. A30 June 2026, extension limited to one year in total
  2. B1 July 2026, as the extension may be up to one further yearCorrect
  3. C1 July 2027, as the extension may be up to two further years
  4. D1 July 2028, as the extension may be up to three further years

Explanation

For inputs the basic period is one year, and on sufficient cause the Commissioner may extend it by a further period not exceeding one year. The maximum is therefore two years from 1 July 2024, that is 1 July 2026. The two-year extension applies only to capital goods, with three years as the base, which is why option C is wrong.

Did you get it right without looking?