Marlow Fabrications is deciding whether to accept a one-off order. The order needs 400 kg of Metal X, which is held in stock and was bought for $12 per kg. Metal X is no longer used in regular production and could be sold as scrap for $5 per kg. Replacing it today would cost $15 per kg. What is the relevant cost of the Metal X for this decision?

The relevant cost is $2,000. The stock is not needed elsewhere, so its opportunity cost is the scrap proceeds forgone, 400 kg at $5. The original purchase price is a sunk cost and replacement cost does not apply because the metal would not be re-bought.

  1. A$2,000Correct
  2. B$4,800
  3. C$6,000
  4. D$2,800

Explanation

The material is not needed for other production, so its relevant cost is the higher of the scrap proceeds forgone and any saving from avoided replacement, and there is no replacement need. Scrap value is 400 x $5 = $2,000. Using historic cost ($4,800) is wrong because it is sunk; using replacement cost ($6,000) is wrong because the material would not be replaced.

Did you get it right without looking?

One question tells you little. A timed set on Cost and management accounting shows your real accuracy, how long you take and where you lose marks.

More Cost and management accounting questions