Meera Exports' registration is cancelled w.e.f. 1 March. On 29 February it held inputs in stock with ITC of ₹40,000. The output tax payable on those goods is ₹52,000. No other goods or capital goods are held. What amount must Meera pay under section 29(5)?

Meera must pay ₹52,000. On cancellation, section 29(5) requires payment of the higher of the input tax credit on inputs in stock (₹40,000) or the output tax payable on those goods (₹52,000). The higher amount is therefore payable.

  1. A₹52,000Correct
  2. B₹40,000
  3. C₹12,000
  4. D₹92,000

Explanation

Section 29(5) requires payment equal to the ITC on inputs held in stock or the output tax payable on such goods, whichever is higher. Higher of ₹40,000 and ₹52,000 is ₹52,000. ₹40,000 picks the lower figure, ₹12,000 is only the difference, and ₹92,000 wrongly adds both.

Did you get it right without looking?

One question tells you little. A timed set on Procedural Compliance under GST shows your real accuracy, how long you take and where you lose marks.

More Procedural Compliance under GST questions