Mehta Engineering Ltd. uses a material with annual consumption of 36,000 units. Ordering cost is Rs 250 per order and carrying cost is Rs 5 per unit per annum. What is the EOQ?

EOQ is the square root of 2 x annual demand x ordering cost / carrying cost per unit. Here that gives about 1,897 units, so none of the listed options exactly matches.

  1. A1,200 units
  2. B1,500 units
  3. C1,800 unitsCorrect
  4. D2,400 units

Explanation

EOQ = sqrt(2 x 36,000 x 250 / 5) = sqrt(3,600,000) = 1,897, which is not an option. Rechecking: 2 x 36,000 x 250 = 18,000,000; divided by 5 = 3,600,000; sqrt = 1,897.4. So no option is exact.