CA Intermediate · Cost and Management Accounting · Unit & Batch Costing
Mehta Engineering uses batch costing for a component. For a batch of 2,000 units, the data are: materials ₹1,20,000, direct wages ₹60,000, machine set-up cost ₹15,000 per batch, and factory overheads absorbed at 50% of direct wages. What is the cost per unit of the batch?
The cost per unit is ₹112.50. Batch cost totals materials ₹1,20,000, wages ₹60,000, set-up ₹15,000 and overheads ₹30,000 (50% of wages), making ₹2,25,000, which divided by 2,000 units gives ₹112.50.
- A₹108.00
- B₹112.50Correct
- C₹115.00
- D₹100.00
Explanation
Overheads = 50% of 60,000 = 30,000. Total = 1,20,000 + 60,000 + 15,000 + 30,000 = 2,25,000. Per unit = 2,25,000 / 2,000 = ₹112.50. Omitting the set-up cost gives 2,10,000/2,000 = ₹105, and ₹108 is not supported.
Did you get it right without looking?
One question tells you little. A timed set on Unit & Batch Costing shows your real accuracy, how long you take and where you lose marks.
More Unit & Batch Costing questions
- Meera Toys Ltd. produces a batch of 500 units. Direct materials are ₹60,000 and direct wages ₹40,000. Factory overhead is absorbed at 150% o…
- Dhruv Engineering manufactures a batch of 500 gears. Costs: materials Rs 60,000; direct wages Rs 40,000; factory overhead is 150% of direct …
- Kaveri Components makes a batch of 1,000 units. Batch cost is Rs 2,40,000. Normal spoilage of 50 units is sold as scrap at Rs 40 each, with …
- A firm makes Product Z in batches of 500 units. Per batch: material Rs 60,000, labour Rs 25,000, and set-up cost Rs 5,000. Factory overheads…
- Which of the following is a feature of batch costing that distinguishes it from unit costing?
- Verma Engineering completes a batch of 800 units at a total cost of ₹4,00,000. It sells the batch at a profit of 25% on selling price. What …