ACCA Applied Skills · Corporate and Business Law (Global) · Introduction to the UN Convention on Contracts for the International Sale of Goods and ICC Incoterms
Norvik Ltd agreed to sell 10 identical machines to Taska Inc under the CISG, delivery in one lot. Norvik delivered the machines on time, but one machine was defective in a way that was not a fundamental breach of the whole contract. Taska wants to cancel the whole contract. What is the position?
Taska may avoid the contract only for a fundamental breach, meaning substantial deprivation of what it was entitled to expect. A defect in one machine that is not fundamental does not qualify, though Taska keeps other remedies such as damages or repair.
- ATaska may avoid the whole contract, because any defect allows avoidance
- BTaska may avoid the contract only if the failure amounts to a fundamental breach, which this one does notCorrect
- CTaska may not claim any remedy because the delivery was on time
Explanation
Avoidance is a last-resort remedy available only for a fundamental breach, meaning substantial detriment that deprives the buyer of what it expected under the contract. A defect in one of ten machines that is not fundamental does not meet this test. Taska can still seek other remedies such as damages or repair, so the third option is wrong.
Did you get it right without looking?
One question tells you little. A timed set on Introduction to the UN Convention on Contracts for the International Sale of Goods and ICC Incoterms shows your real accuracy, how long you take and where you lose marks.
More Introduction to the UN Convention on Contracts for the International Sale of Goods and ICC Incoterms questions
- Mora Ltd sells specialised packaging to Nest Co under a CISG contract. Delivery is late by two weeks, but Nest still receives usable goods a…
- Jarrow Ltd (contracting state A) agrees to build and install a complete production line for Kestrel Ltd (contracting state B). Kestrel will …
- Altus Ltd, based in State A, agrees to sell industrial machinery to Brevin Co, based in State B, for use in Brevin's factory. Both states ar…
- Isidore Ltd offers to sell goods to Jarvis Co. Jarvis does not reply but, in accordance with practices the parties have established between …
- Altus Ltd, based in Country A, emails Borra SA in Country B offering to sell 500 tonnes of steel at a stated price, delivery in June. The em…
- Jorvik Ltd, in a Contracting State, sells a consignment of timber to Kestrel Ltd, in another Contracting State. The timber is defective and …