Orbit Co is evaluating a product with a life cycle of three phases. Pre-production design and development costs are $200,000. Production and selling costs over the life are $600,000. Decommissioning and environmental restoration costs at the end of life are $100,000. Total lifetime sales volume is 50,000 units. Orbit currently ignores decommissioning in its costing. What is the difference between the full life cycle cost per unit and the cost per unit currently calculated?

The full life cycle cost is $2.00 per unit higher. Total life cycle cost is $900,000, or $18 per unit over 50,000 units, while the current approach gives $800,000, or $16 per unit. The $100,000 decommissioning cost spread over 50,000 units makes up the $2 gap.

  1. A$2.00 per unit higherCorrect
  2. B$4.00 per unit higher
  3. C$2.00 per unit lower
  4. D$18.00 per unit higher

Explanation

Full life cycle cost = 200,000 + 600,000 + 100,000 = $900,000, or $18.00 per unit over 50,000 units. Current costing excludes decommissioning, giving $800,000 / 50,000 = $16.00. The difference is $2.00 per unit, equal to 100,000 / 50,000. The $18.00 option confuses the full cost with the difference.