Original standard price of a raw material was Rs 50 per kg. Because of market changes the revised (ex-post) standard price is Rs 56 per kg. Standard quantity for actual output is 1,900 kg. Actual purchase and usage was 2,000 kg at Rs 58 per kg. What is the total operating variance for this material (price plus usage, measured against the revised standard)?

The total operating variance is Rs 9,600 Adverse, being Rs 4,000 adverse price variance plus Rs 5,600 adverse usage variance, both measured against the revised standard price of Rs 56. The Rs 11,400 planning variance is excluded because it is uncontrollable.

  1. ARs 9,600 AdverseCorrect
  2. BRs 21,000 Adverse
  3. CRs 11,400 Adverse
  4. DRs 4,000 Adverse

Explanation

Operating price variance = (56 - 58) x 2,000 = Rs 4,000 Adverse. Operating usage variance = (1,900 - 2,000) x 56 = Rs 5,600 Adverse. Total operating variance = Rs 9,600 Adverse. Planning variance = (50 - 56) x 1,900 = Rs 11,400 Adverse; together they give the Rs 21,000 Adverse total variance against the original standard, which is not the operating variance.

Did you get it right without looking?

One question tells you little. A timed set on Variance Analyses shows your real accuracy, how long you take and where you lose marks.

More Variance Analyses questions