Ostrava plc agrees to buy 2,000 units from Lindqvist AB under the CISG. The contract fixes a price but gives no payment date, and no other rule on timing is agreed. Lindqvist places the goods at Ostrava's disposal on 10 May. Under the CISG, when must Ostrava pay?
Ostrava must pay when Lindqvist places the goods or the documents controlling them at its disposal in accordance with the contract. The CISG sets no fixed period such as 90 days, and resale or year end is irrelevant to timing.
- AWithin 90 days of the contract being made
- BWhen Lindqvist places the goods or documents at Ostrava's disposal in accordance with the contractCorrect
- COnly after Ostrava has fully inspected and resold the goods
- DOn the last day of the calendar year in which the contract was concluded
Explanation
Where no date is fixed, the buyer must pay when the seller places either the goods or documents controlling their disposal at the buyer's disposal. The seller may make payment a condition of handing over. There is no automatic 90-day or year-end term, and resale is irrelevant.
Did you get it right without looking?
One question tells you little. A timed set on Obligations of the seller and buyer, and provisions common to both shows your real accuracy, how long you take and where you lose marks.
More Obligations of the seller and buyer, and provisions common to both questions
- Irving Co bought goods from Jarrow Ltd under the CISG. On inspection, Irving found the goods defective but did not notify Jarrow of the lack…
- Ibex Ltd contracts to sell goods to Jorvik Co under the CISG. The contract involves carriage but states no delivery date and no place beyond…
- Under the CISG, Brandt GmbH is to deliver 12 monthly instalments of components to Vale Inc. The fourth delivery is defective, which gives Va…
- A seller in Country A agrees to sell machine parts to a buyer in Country B under a CISG contract. The contract requires the seller to hand t…
- Altura Ltd agreed to sell 500 machine parts to Brevik GmbH under a contract governed by the CISG. Altura delivered the parts, but they were …
- Garnet Ltd, a buyer under a CISG contract, refuses to take delivery of goods that the seller, Hollin Co, tendered on the agreed date and whi…