CA Foundation · Business Laws · The Indian Contract Act, 1872
Ramesh agreed to buy a painting from Sheela for Rs 5 lakh, and the contract says that if Ramesh breaches, he shall pay Rs 1 lakh. Ramesh breaches, but Sheela proves actual loss of only Rs 40,000. Under Section 74, what can Sheela recover?
Sheela can recover Rs 40,000. Under Section 74 the stipulated Rs 1 lakh is only a ceiling, and the court awards reasonable compensation not exceeding it. Since the proved loss is Rs 40,000, that is the reasonable compensation. Indian law does not treat the clause as void.
- AReasonable compensation not exceeding Rs 1,00,000, here Rs 40,000Correct
- BRs 1,00,000 in all cases
- CRs 5,00,000
- DNothing, as the clause is a penalty and void
Explanation
Under Section 74, where a sum is named as payable on breach, the aggrieved party is entitled to reasonable compensation, not exceeding the amount named, whether or not actual loss is proved. Where the loss is proved to be Rs 40,000, reasonable compensation is Rs 40,000, within the Rs 1 lakh ceiling. The stipulated sum is a maximum, not automatic. Indian law does not void such clauses.
Did you get it right without looking?
One question tells you little. A timed set on The Indian Contract Act, 1872 shows your real accuracy, how long you take and where you lose marks.
More The Indian Contract Act, 1872 questions
- Ketan and Lata, both of Surat, agree that Ketan will pay Rs 5 lakh to Lata if she does not marry anyone for the next 10 years. Lata remains …
- Sunita, a coaching centre owner in Indore, agrees to sell her flat to Rajesh. Later it is found that the flat was destroyed in a fire a day …
- Ravi, a shopkeeper in Jaipur, threatens to file a false police complaint against his employee Sunita unless she signs an agreement to sell h…
- Kiran agrees to sell 100 bags of rice to Lalit, delivery on 1 March, time being stated to be of the essence. Kiran fails to deliver on 1 Mar…
- Nisha, a minor, is the beneficiary of a contract in which she is to receive Rs 40,000 from Omkar when she turns 18, in exchange for work she…
- Vikram, a tailor, agrees to stitch 20 uniforms for Sharma School. He breaches the contract. Sharma School claims Rs 2,00,000 for loss of a p…