Rao Pvt Ltd (Hyderabad) supplies a machine to Iyer Ltd for Rs 6,00,000 plus GST at 18%. Rao and Iyer are not related. The contract is for Rs 6,00,000 and Iyer additionally agrees to pay Rs 40,000 for installation (done by Rao, billed in same invoice) and Rao separately pays Rs 25,000 for insurance of the machine while in transit, which Rao recovers from Iyer. Iyer also pays directly Rs 15,000 to a third party for a training programme; this was not required by Rao. Rao incurs Rs 12,000 for commissioning and bills it as part of the installation charge of Rs 40,000. Compute the value of supply.

The value of supply is Rs 6,65,000. Price of Rs 6,00,000, installation of Rs 40,000 and insurance of Rs 25,000 recovered from the buyer are included. Commissioning is already part of installation, and training paid by the buyer to a third party is not consideration.

  1. ARs 6,40,000
  2. BRs 6,65,000Correct
  3. CRs 6,80,000
  4. DRs 6,52,000

Explanation

Value = price 6,00,000 + installation 40,000 (commissioning of Rs 12,000 is already within it, so not added again) + insurance recovered 25,000 = 6,65,000. The training paid by the buyer directly to a third party for its own purpose is not consideration to the supplier and is excluded. Rs 6,52,000 and Rs 6,80,000 double count commissioning or add training.

Did you get it right without looking?

One question tells you little. A timed set on Value of Supply shows your real accuracy, how long you take and where you lose marks.

More Value of Supply questions