CMA Final · Strategic Cost Management · Relevant Cost Analysis

Rohan Engineering has a machine-hour limit of 1,200 hours. Product P gives contribution Rs 90 per unit using 3 machine hours; product Q gives Rs 100 per unit using 4 hours; product R gives Rs 60 per unit using 2 hours. Maximum demand is 200 units each. Which production plan maximises total contribution?

The best plan is P 200, R 200 and Q 50 units, giving Rs 35,000. Contribution per limiting machine hour is Rs 30 for P and R and Rs 25 for Q, so P and R are made to full demand and the remaining 200 hours go to Q.

  1. AP 200, R 200, Q 50; contribution Rs 63,000
  2. BP 200, Q 150, R 0; contribution Rs 33,000
  3. CP 200, R 200, Q 50; contribution Rs 35,000Correct
  4. DP 200, Q 200, R 0; contribution Rs 38,000

Explanation

Contribution per hour: P 30, Q 25, R 30. P and R tie at 30, then Q. P 200 uses 600 hours, R 200 uses 400, leaving 200 hours for Q = 50 units. Contribution = 18,000 + 12,000 + 5,000 = Rs 35,000. Rs 63,000 is an arithmetic error, and Q-heavy plans give lower per-hour returns.