Rohan Engineering has a machine-hour limit of 1,200 hours. Product P gives contribution Rs 90 per unit using 3 machine hours; product Q gives Rs 100 per unit using 4 hours; product R gives Rs 60 per unit using 2 hours. Maximum demand is 200 units each. Which production plan maximises total contribution?
The best plan is P 200, R 200 and Q 50 units, giving Rs 35,000. Contribution per limiting machine hour is Rs 30 for P and R and Rs 25 for Q, so P and R are made to full demand and the remaining 200 hours go to Q.
- AP 200, R 200, Q 50; contribution Rs 63,000
- BP 200, Q 150, R 0; contribution Rs 33,000
- CP 200, R 200, Q 50; contribution Rs 35,000Correct
- DP 200, Q 200, R 0; contribution Rs 38,000
Explanation
Contribution per hour: P 30, Q 25, R 30. P and R tie at 30, then Q. P 200 uses 600 hours, R 200 uses 400, leaving 200 hours for Q = 50 units. Contribution = 18,000 + 12,000 + 5,000 = Rs 35,000. Rs 63,000 is an arithmetic error, and Q-heavy plans give lower per-hour returns.
Did you get it right without looking?
One question tells you little. A timed set on Relevant Cost Analysis shows your real accuracy, how long you take and where you lose marks.
More Relevant Cost Analysis questions
- Mahesh Engineering has spare capacity of 2,000 machine hours. A special order needs 1,500 machine hours. The variable cost is Rs 90 per hour…
- Mehta Fabricators holds 400 kg of a special alloy bought two years ago at Rs 300 per kg. The alloy has no other use in the firm. It can be s…
- Pooja Foods needs 800 kg of Material X for a job. Stock is 500 kg bought at Rs 40 per kg; its current replacement cost is Rs 52 per kg and i…
- Kaveri Foods sells a product at Rs 50 per unit with variable cost Rs 30. A special order for 2,000 units at Rs 38 per unit arrives. Acceptin…
- Meera Industries produces a joint product that is sold at the split-off point for Rs 40 per kg. It can be processed further at an additional…
- Sagar Foods makes 10,000 units of a component at a cost per unit of: materials Rs 30, labour Rs 20, variable overhead Rs 10, and fixed overh…