Skip to content

CMA Intermediate · Cost Accounting · Batch Costing

Setup cost for a batch of 500 units is ₹10,000. Material is ₹60 per unit and labour is ₹40 per unit. Other overheads are absorbed at ₹10 per unit. What is the cost per unit?

Cost per unit is ₹130. Setup cost of ₹10,000 spread over 500 units gives ₹20 per unit, which is added to material ₹60, labour ₹40 and overheads ₹10. Ignoring setup cost would wrongly give ₹110.

  1. A₹130Correct
  2. B₹110
  3. C₹150
  4. D₹120

Explanation

Setup cost per unit is 10,000/500 = ₹20. Cost per unit = 60 + 40 + 10 + 20 = ₹130. The ₹110 option omits setup cost; ₹150 would double count setup.

Did you get it right without looking?

One question tells you little. A timed set on Batch Costing shows your real accuracy, how long you take and where you lose marks.

More Batch Costing questions