CMA Foundation · Fundamentals of Financial and Cost Accounting · Cost, Cost Centre, Cost Unit and Cost Drivers
Sharma Components Ltd has a set-up cost pool of Rs 1,20,000 for the period. The pool is driven by the number of production runs. Product P had 12 runs, Product Q had 28 runs, so total runs were 40. What set-up cost is assigned to Product Q under activity based costing?
Product Q is assigned Rs 84,000. The set-up pool of Rs 1,20,000 divided by 40 total runs gives Rs 3,000 per run, and Q had 28 runs. The Rs 36,000 figure belongs to Product P, which had only 12 runs.
- ARs 36,000
- BRs 60,000
- CRs 84,000Correct
- DRs 1,20,000
Explanation
Rate per run = 1,20,000 / 40 = Rs 3,000. Product Q: 28 x 3,000 = Rs 84,000. Check: P gets 12 x 3,000 = 36,000, and 36,000 + 84,000 = 1,20,000. Rs 36,000 is the amount for P, the wrong product.
Did you get it right without looking?
One question tells you little. A timed set on Cost, Cost Centre, Cost Unit and Cost Drivers shows your real accuracy, how long you take and where you lose marks.
More Cost, Cost Centre, Cost Unit and Cost Drivers questions
- A firm's cost accounting system records that a machine's depreciation of Rs 30,000 is charged to a product costing Rs 2,00,000 in materials.…
- Sharma Components Ltd has a set-up cost pool of Rs 3,60,000 for a period, and 120 set-ups are performed. Product Alpha needs 30 set-ups and …
- A goods transport company in Nagpur runs trucks that carried the following in a month: Truck A 10 tonnes over 200 km, Truck B 20 tonnes over…
- Bharat Auto's Component Division has operating profit of ₹18,00,000 and capital employed of ₹90,00,000. The division is an investment centre…
- In activity based costing, the correct sequence of the basic steps is:
- Which of the following is a feature that distinguishes cost accounting from financial accounting?