CMA Final · Indirect Tax Laws and Practice · Manufacture in Bond
Sharma Traders, the importer under a section 59 bond, transfers part of the warehoused goods to Verma Exports, another person. What must Verma Exports do under section 59?
Verma Exports must execute its own bond under sub-section (1) or (2) and furnish the security specified in sub-section (3). Section 59(5) imposes both obligations on a transferee of the whole or part of the goods.
- ANothing, as Sharma Traders' bond covers the transferred goods
- BExecute a bond in the manner of sub-section (1) or (2) and furnish security as specified under sub-section (3)Correct
- CExecute a bond only, since security is required only from the original importer
- DPay the duty immediately and execute no bond
Explanation
Section 59(5) provides that where goods or any part are transferred to another person, the transferee must execute a bond under sub-section (1) or (2) and furnish security under sub-section (3). Option 3 is wrong because security is also required.
Did you get it right without looking?
One question tells you little. A timed set on Manufacture in Bond shows your real accuracy, how long you take and where you lose marks.
More Manufacture in Bond questions
- Sagar Foods Ltd. executed a warehousing bond for goods. Of these goods, 60% have been cleared for home consumption and 30% exported; the bal…
- Sharma Metals Ltd has executed a warehousing bond under Section 59 for goods stored in Warehouse A. The goods are later moved wholly to Ware…
- Imported materials are used under Section 65 to manufacture goods in a warehouse. Duty on the materials is 25% and duty on the finished good…
- Under Section 59(5) of the Customs Act, 1962, when the whole or part of warehoused goods is transferred by the importer to another person, w…
- Kapoor Industries imported goods for warehousing. Duty assessed was Rs 5,00,000 and a bond under section 59(1) was executed. Goods with duty…
- Imported materials are used under section 65 to manufacture goods in a warehouse. The duty rate on the materials is 20% and on the finished …