Standard Costing: Sharma Industries has a standard of 8 labour hours per unit at Rs 30 per hour. In a month, 1,000 units were produced. Hours paid were 8,400, of which 300 were idle due to a power failure. Actual wages paid were Rs 2,60,400. What is the labour efficiency variance?
The labour efficiency variance is Rs 3,000 adverse. Standard hours for 1,000 units are 8,000, while hours actually worked, excluding 300 idle hours, are 8,100. The 100 extra hours at the standard rate of Rs 30 give Rs 3,000 adverse.
- ARs 9,000 AdverseCorrect
- BRs 3,000 Adverse
- CRs 900 Adverse
- DRs 9,000 Favourable
Explanation
Standard hours for actual output = 1,000 x 8 = 8,000. Actual hours worked = 8,400 - 300 = 8,100. Efficiency variance = (8,000 - 8,100) x 30 = Rs 3,000 Adverse. Re-checking: 100 x 30 = 3,000, so the correct figure is Rs 3,000 Adverse; option A uses paid hours 8,400 (400 x 30 = 12,000 is not it either) and is wrong.
Did you get it right without looking?
One question tells you little. A timed set on Standard Costing shows your real accuracy, how long you take and where you lose marks.
More Standard Costing questions
- Which of the following best describes a 'favourable' variance in standard costing?
- Sundaram Foods budgeted 10,000 units at a standard selling price of Rs 100 and standard cost of Rs 70 per unit. Actual sales were 9,000 unit…
- Standard labour cost for a unit of product at Kaveri Engineering is 5 hours at Rs 80 per hour. In a month, 1,000 units were produced. Actual…
- Bharat Chemicals uses a standard mix for 100 kg of output: 60 kg of A at Rs 50 per kg and 50 kg of B at Rs 40 per kg (standard loss 10 kg). …
- Kaveri Plastics set a standard of 4 kg of resin per unit of output at Rs 50 per kg. In March it produced 1,000 units, using 4,200 kg of resi…
- Standard Costing: Which one of the following best describes a 'basic standard' in standard costing?